Near term production - Bomboko
- Nine alluvial licences adjacent to Guinea's only diamond mine, Aredor
- Semi-industrial mining licence approved by Ministry of Mines January 2005 renewable after 3 years
- Extensive sampling has identified a potential resource of up to 750,000 cts at grades up to 28 cpht, mainly gem quality
- 200 carats and 4 large stones (9.2, 4.5, 4.2 and 3.8) recovered from bulk sampling
- Mine on stream since March 2009
- Production commenced April 2009
- Operations commenced with a 10 foot Pan Plant capable of treating 7,000 tonnes a month
- 16 foot Pan Plant supported by a 46 tonne excavator being installed, increasing production to 18,000 tonnes a month